top of page

The Dream

  • 2 new Ballfields (Softball and Baseball)

  • Scoreboard and Lights for each field

  • Parking for 200+ vehicles

  • Trees and landscape enhancements

  • Possible walking/jogging path

 

The Plan

PHASE 1  - $368,750 budgeted - $295,381 actual - COMPLETED Oct '19

  • Land acquisition (purchased 12 acres south of the current complex)

  • Surveys, site preparation, seeding and parking lot development

 

PHASE 2 - $384,500 budgeted - STARTED Nov '19

  • Soil, seed, dugouts, fencing, backstops, utilities, gates, irrigation, infield, shed

​

PHASE 3 - $738,500 estimate

  • Scoreboards, bleachers, lighting, concession, crow's next, restroom construction

 

 

TOTAL ESTIMATED PROJECT COST $1,491,750

Malcolm New Basball Field From SouthEast
Malcolm New Softball Field From North